More Egress Window

Had to dig out a lot more, but finally got the permeable weed barrier in, and about 6" of leveled, crushed rock.  I've also cut 3 levels of the framing.
I have a bunch of scrap plywood and 2 doors serving to keep and dirt from caving in or rolling down while I work on the framing.  These aren't firmly bolted in place yet.  Want to have the code inspectors check it out before I firm that up.  Plus, I ran out of the framing wood, will need to get some more.

Comments

Popular posts from this blog

Ugly Float and Tape

Getting started on the float and tape job on the upstairs half bath.  Pretty ugly so far. This is just the first coat, which is really intended to just get the tape down.  Looks ugly, but it's actually not bad.  Won't know for sure how it will look till the last coat.  Plan is to do a texture-free level 5 finish.  Not sure if I'll be able to pull it off or not, worst case if it doesn't pan out I can just throw some texture up.

Back Wall Done

 Finally 100% done with the back wall of the house.  Windows installed, trim done, and paint. The windows will probably get pretty messy until I have time to install the edging and river rock along the edge, but that will come later.

Ready for drywall

Got all the code approvals, ready to put up drywall