Skip to main content

Foundation Sealing

There were signs of minor water seepage into the masonry.  This might have been due to the chimney cap, but I wanted to make sure everything was sealed up right.  So I dug around the foundation.  I plan to do this all the way around the back foundation, as I plan to do the steel planter there.
While the area under the concrete was fine, and there is a French drain all around the foundation, it seemed clear that the rock around the chimney had become clogged with dirt, and it seemed that any water that came in contact with that base wouldn't have anything preventing it from seeping in.  Even found an old rusted ash door about 1' down.  There were also some odd locations, evenly spaced along the base of the foundation, where there were small wood pieces that penetrated all the way through.  I could even see those on the backside of the planter. 

So, I used simple mortar to fill those, and then sealed everything with a tar based foundation sealant.  I don't expect the mortar to repel water, just to provide a good surface for the sealant to adhere.

This also provides some sealant between the lead (I assume) drip trim and the foundation itself.  It's probably overkill, but I wanted to make sure it was done right.

Comments

Popular posts from this blog

Ugly Float and Tape

Getting started on the float and tape job on the upstairs half bath.  Pretty ugly so far. This is just the first coat, which is really intended to just get the tape down.  Looks ugly, but it's actually not bad.  Won't know for sure how it will look till the last coat.  Plan is to do a texture-free level 5 finish.  Not sure if I'll be able to pull it off or not, worst case if it doesn't pan out I can just throw some texture up.

Back Wall Done

 Finally 100% done with the back wall of the house.  Windows installed, trim done, and paint. The windows will probably get pretty messy until I have time to install the edging and river rock along the edge, but that will come later.

Bathroom Waterproofing

Waterproofing the shower.  1 primer coat, 5 coats on the walls, 7 on the pan.  Tested and approved by the inspector.  Next is upper pan and then tile.