Got the theater wall wood finished, and all of the cables run internally.

All that is left is the top trim, the ceiling panels for the lights, and some trim items.

Comments

Popular posts from this blog

Bathroom Waterproofing

Waterproofing the shower.  1 primer coat, 5 coats on the walls, 7 on the pan.  Tested and approved by the inspector.  Next is upper pan and then tile.

Harry Potter Hole

Harry Potter Hole, as my friends started calling it, has had its internal trim installed, and I've put paint on the shelving below it.  This will look good once the flooring is installed.

Laundry and Bathroom

 Got the backsplash done in the laundry room, next I need to finish the plinth and that room is done. And have the primer coat. And first sealing coat of waterproofing done one the basement bathroom It will probably need 2-3 more coats before it's ready for inspection.